• Project Name:  Construction of National Motorway M-4 Shorkot-Khanewal Section Project-ICB-M4-IIIA in Pakistan
  • progress)
  • Contract Value: 2.7hundred million SAR
  • Contract Duration: 21Months
  • Location: Sauerkot, Jaipur
  • Project Name:  General Construction Contract Lot 2 of Xi ‘an Subway Line 10 Phase I Project (in progress)
  • Contract Value: 1.31 billion SAR
  • Contract Duration: 48 Months
    Location: Xi’an
  • Project Features:Total investment 3.501 billion SAR, the  Northwest China’s first road-subway-rail bridge.